Ekibastuz–Kokshetau high-voltage line

From Kazakhstan Encyclopedia

Template:Infobox power transmission line

File:Insulators compare.jpg
PSK-300A and PS-400A (U400A) disc suspension insulators used on 1150 kV powerlines in comparison with common U70BL insulator

The Ekibastuz–Kokshetau high-voltage line is an alternating current electrical power transmission line in Kazakhstan from Ekibastuz to Kokshetau. It was the first commercially used power line in the world which operated at 1,150 kV, the highest transmission line voltage in the world. It is a part of the Itatsk (Sharypovo)–Barnaul–Ekibastuz–Kokshetau–KostanayChelyabinsk (Siberia–Kazakhstan–Urals) transmission system, which was designed to transfer electricity from Siberia and Kazakhstan to industrial region in Urals.[1]

Designated as power line number 1101, it runs Template:Convert from Ekibastuz to Kokshetau. It is mounted on transmission towers with an average height of Template:Convert. The weight of the conductors between the spans is approximately 50 tons. With a voltage of 1,150 kV the line had a maximum transfer capacity of 5,500 MW.[2]

The whole length of the Siberia–Kazakhstan–Urals line is Template:Convert, of which Template:Convert is located in Kazakhstan and the rest is located in Russia.[3]

History

In 1973, the Soviet Union built a three-phase UHV experimental test circuit over a kilometre long at the Beily Rast substation, near Dmitrov in Moscow region. In 1978, a 270 km UHV test line for industrial use was built from Sharypovo to Novokuznetsk. In 1985, this test line became part of the Siberia–Urals line. At the time, no other country had an operational UHV line of this voltage, although several other countries were running experiments.[4][3]

On 24 March 1977, the Central Committee of the Communist Party of the Soviet Union and the Council of Ministers of the Soviet Union took a decision of construction of the Ekibastuz–Centre (Tambov) 1,500 kV direct current line.[1][5] This line was under construction but was never finished.[1] In addition, the Ekibastuz–Urals line was planned. Construction of this line started in 1980. The Ekibastuz–Kokshetau line was commissioned in the end of July 1985.[1][5] The technical design of the line was done by Energosetproekt. The main contractor was Specsetstroy, while contractors for the 1,150 kV substations were Ekibastuzenergostroy and Yuzhuralenergostroy. Equipment for substations were provided by Zaporozhtransformator, Elektrosila, and Uralelektrotyazhmash.[5]

In 1988, this 1,150 kV line was prolonged to Kostanay. By 1990, the whole line from Barnaul to Chelyabinsk was built; however, as 1,150 kV substations were built only in the territory of Kazakhstan, the rest of this system operated at 500 kV. After dissolution of the Soviet Union in 1991, the whole Siberia–Urals transmission system was downgraded to 500 kV.[1][6] In 1998, the Siberia–Urals line was prolonged from Barnaul to Itatsk.

Sites

Name Coordinates
Chelyabinsk Template:Coord
Kostanay Template:Coord
Kokshetau Template:Coord
Ekibastuz Template:Coord
Barnaul Template:Coord
Sharypovo Template:Coord

References

Template:Reflist

Bibliography

  • Research Institute of Development Assistance (Japan), Regional cooperation in central Asia : focusing on infrastructure development, The Overseas Economic Cooperation Fund, Japan, Research Papers No. 27, July 1998 Template:OCLC.
  • Template:Cite book
  • Template:Cite book

Template:Portal
Cite error: <ref> tags exist, but no <references/> tag was found