Karabakh oilfield

From Kazakhstan Encyclopedia
Revision as of 19:45, 4 April 2017 by Lklundin (Talk)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Template:Infobox oil field

Karabakh (Azerbaijani: Qarabağ) is an offshore oil and gas field in the Caspian Sea, located Template:Convert east of Baku, Azerbaijan, in the northern part of Absheron archipelago.<ref name=Nefte.ru>НЕФТЕГАЗОДОБЫЧА В СТРАНАХ СНГ</ref> The Karabakh block is located Template:Convert northeast of another big field - Azeri-Chirag-Guneshli (ACG) <ref name="Azerbaijan International"> Template:Cite journal </ref>

History

A production sharing agreement (PSA) for exploration and development of the Karabakh field was signed on 10 November 1995. It is considered to be Azerbaijan's second major contract for development of oil fields in the Caspian Sea after ACG project. The agreement had a development and production period of up to 25 years with possible extension of 5 more years<ref name="Azerbaijan International"/> On 13 February, 1996 the agreement was ratified by the Parliament of Azerbaijan Republic. The contract came into force on 28 February 1996. On 4 June 1996, the companies holding an interest in the project established a joint consortium and named it Caspian International Petroleum Company (CIPCO).<ref name="Azerbaijan International-2"> Template:Cite journal </ref> CIPCO officially started operating in August 1996. On 26 January 1999, CIPCO announced it would cease its operations. According to the management of the consortium, the development of the field was not economically profitable at this stage. As per the president of the consortium, James Tilley, the drilling of 3 wells indicates the reservoir holds no more than 30 million tonnes of oil. CIPCO officially completed its operations on 23 February 1999. Total expenses incurred constituted nearly $100 million.<ref name=Nefte.ru/><ref> Template:Cite news</ref> In April, 2006, SOCAR announced it would be able to develop the field itself without foreign investment. Total expenditures would reach close to $200 million. According to the Vice-President of SOCAR, Khoshbakht Yusifzade, the feasibility study of two of the drilled wells revealed availability of 10 million tonnes of oil and 5-6 billion cubic meters of natural gas which draws a clear picture on recoverable reserves as a whole.<ref> Template:Cite news</ref>

Ownership

Shareholders of CIPCO have the following stakes in Karabakh field:

Company Interest
LUKAgip JV 45%
Pennzoil 30%
LUKOIL 12.5%
SOCAR 7.5%
Agip 5%

According to the PSA agreement, the total bonus to be paid to Azerbaijan would have been $135 million. Total capital expenditures for the project were to be $1.7 billion<ref name=Nefte.ru/> $1.3 billion was planned for operating costs.<ref name="Azerbaijan International"/>

Production

According to preliminary data, an estimated Template:Bbl to t<ref name="Azerbaijan International"/> of oil is believed to lay in the field. Depth of the strata is Template:Convert. The agreement between the parties stipulated a 3 year feasibility study (seismic study and drilling of 3 wells). The period could have been extended if necessary. First production was planned for end of 2000. The drilling activities were conducted by US-Azerbaijan joint venture Caspian Drilling Company established by SOCAR and Santa Fe<ref name=Nefte.ru/>